| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIS-17 | Firme de concreto armado sobre losa de 5 cms | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.150000 | $8.00 | $1.20 |
| AGREGADO 01 | ARENA | m3 | 0.052000 | $62.00 | $3.22 |
| POLIETILENO | POLIETILENO DE 6MCRAS | M2 | 1.100000 | $15.00 | $16.50 |
| Suma de Material | $20.92 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.133333 | $717.71 | $95.69 |
| Suma de Mano de Obra | $95.69 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.052500 | $903.30 | $47.42 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 5.770000 | $14.89 | $85.92 |
| Suma de Auxiliar | $133.34 | ||||
| Costo Directo | $249.96 |