| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-002 | CONTRATRABE CT-2 EDIFICIO 15 N DE 0.40*1.30 CON 16#8 , 6#5 Y ESTRIBOS DOBLES DEL #3 A/C 20 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 0.520000 | $80.00 | $41.60 |
| Suma de Material | $41.60 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 2.600000 | $170.37 | $442.96 |
| CONCRETO BOMB 300 | CONCRETO PREMEZCLADO FC=300 KG/CM2 BOMBEABLE | M3 | 0.520000 | $1,377.66 | $716.38 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 87.000000 | $14.89 | $1,295.43 |
| Suma de Auxiliar | $2,454.78 | ||||
| Costo Directo | $2,496.38 |