| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-40 | FIRME DE CONCRETO DE 10 CMS DE ESPESOR F'C= 200 KG/CM2 CON PLASTICO Y 1 MALLA 66-10,10 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.150000 | $8.00 | $1.20 |
| AGREGADO 01 | ARENA | m3 | 0.052000 | $62.00 | $3.22 |
| POLIETILENO | POLIETILENO DE 6MCRAS | M2 | 1.100000 | $15.00 | $16.50 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.100000 | $10.12 | $11.13 |
| Suma de Material | $32.06 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.133333 | $717.71 | $95.69 |
| Suma de Mano de Obra | $95.69 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.105000 | $903.30 | $94.85 |
| Suma de Auxiliar | $94.85 | ||||
| Costo Directo | $222.60 |