| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-09 | Z1 DE 1.7*1.7 DADO DE 0.45*0.45 PARR #4 A/C 13 , 8#4 EN DADO Y ESTRIBOS DE #2 A/C 20 DOBLES | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 1.250000 | $80.00 | $100.00 |
| Suma de Material | $100.00 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 3.530000 | $170.37 | $601.41 |
| CONCRETO BOMB 300 | CONCRETO PREMEZCLADO FC=300 KG/CM2 BOMBEABLE | M3 | 1.250000 | $1,377.66 | $1,722.08 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 109.330000 | $14.89 | $1,627.92 |
| Suma de Auxiliar | $3,951.40 | ||||
| Costo Directo | $4,051.40 |