| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TC-03 | LOSA TAPA DE CONCRETO PREFABRICADA P-15 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.150000 | $903.30 | $135.50 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 6.000000 | $14.89 | $89.34 |
| CE-02-01 | CIMBRA COMUN | M2 | 1.000000 | $170.37 | $170.37 |
| Suma de Auxiliar | $395.21 | ||||
| Costo Directo | $395.21 |