| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALBER-001 | MURO DE CONCRETO ARMADO ALBERCA, CON VARILLA DE 1/2" @ .20 CM AMBOS SENTIDOS, DOBLE | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 0.120000 | $80.00 | $9.60 |
| Suma de Material | $9.60 | ||||
| Auxiliar | |||||
| CONCRETO BOMB 250 | CONCRETO PREMEZCLADO FC=250 KG/CM2 BOMBEABLE | M3 | 0.120000 | $1,417.77 | $170.13 |
| CIMBRA | Cimbra aparente incluye: materiales y mano de obra. | M2 | 2.000000 | $158.04 | $316.08 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 1.700000 | $14.89 | $25.31 |
| Suma de Auxiliar | $511.53 | ||||
| Costo Directo | $521.13 |