| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| P3N-008 | IRATEN EN PLAFON LOSA CUARTOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Contrato | |||||
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| P3N-008_SC | Subcontrato de P3N-008 | M2 | 1.000000 | $50.00 | $50.00 |
| Suma de Contrato | $600.00 | ||||
| Costo Directo | $600.00 |