| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| LOSA-001- | LOSA TERRAZA ACABADO CON IMPERMEABILIZANTE INTEGRAL FESTERGRAL JUNTAS DE EXPANCION ESTACIONAMIENTO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 0.233700 | $80.00 | $18.70 |
| CASETON | CASETON STIROLITE 50X50X30 CMS | pza | 2.352000 | $45.00 | $105.84 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.100000 | $10.12 | $11.13 |
| VIGUETA VARIAS MED. | VIGUETAS DE ALMA ABIERTA VARIAS MEDIDAS FR 14 CMS. | PZA | 2.780000 | $16.36 | $45.48 |
| Suma de Material | $181.15 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.200000 | $673.86 | $134.77 |
| Suma de Mano de Obra | $134.77 | ||||
| Auxiliar | |||||
| CONCRETO BOMB 250 | CONCRETO PREMEZCLADO FC=250 KG/CM2 BOMBEABLE | M3 | 0.085000 | $1,417.77 | $120.51 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 4.000000 | $14.89 | $59.56 |
| Suma de Auxiliar | $180.07 | ||||
| Costo Directo | $495.99 |