| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PY-06 | BOQUILLA | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA | PolÃn 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.300000 | $6.70 | $2.01 |
| AGREGADO-003 | AGUA | M3 | 0.020000 | $12.40 | $0.25 |
| Suma de Material | $2.26 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.050000 | $717.71 | $35.89 |
| Suma de Mano de Obra | $35.89 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO 1:5 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.003938 | $600.35 | $2.36 |
| Suma de Auxiliar | $2.36 | ||||
| Costo Directo | $40.51 |