| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESCVI-01 | RAMPA DE ESCALERA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.200000 | $673.86 | $134.77 |
| Suma de Mano de Obra | $134.77 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 1.000000 | $170.37 | $170.37 |
| CONCRETO BOMB 250 | CONCRETO PREMEZCLADO FC=250 KG/CM2 BOMBEABLE | M3 | 0.233700 | $1,417.77 | $331.33 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 18.000000 | $14.89 | $268.02 |
| Suma de Auxiliar | $769.72 | ||||
| Costo Directo | $904.49 |