| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST3-01 | SUMINISTRO Y MONTAJE DE ESTRUCTURA METALICA DE VIGAS IPR , COLOCACION DE ANGULOS , HABILITADO Y COLOCACION DE PLACAS DE CONEXIONES , SOLDADURA A LAS VIGUETAS Y NERVIOS DE TEMPERATURA , APLICACION DE PRIMARIO CROMATO DE ZINC PARA TRABES DE VIGA IPR DEL EDIFICIO DE 1 N | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO IR 254X32.90 | PERFIL ESTRUCTURAL IR DE 254 X 32.9 | kg | 1.050000 | $10.50 | $11.03 |
| GAS P/CORTES | GAS P/ CORTES | KG | 0.008614 | $3.96 | $0.03 |
| OXIGENO | OXIGENO | M3 | 0.006000 | $38.50 | $0.23 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.002106 | $31.25 | $0.07 |
| PRIMER INORG. | PRIMER INORGANICO DE ZINC GALVADUR | litro | 0.015000 | $65.00 | $0.98 |
| THINER | THINER | LT | 0.020000 | $12.00 | $0.24 |
| SOLDADURA 70E-XX | SOLDADURA 70E-XX | kg | 0.007000 | $25.00 | $0.18 |
| Suma de Material | $12.75 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.005000 | $611.86 | $3.06 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.005000 | $611.86 | $3.06 |
| CUADRILLA 19 | Cuadrilla de pintores(1 OF. PINTOR + 2 AYUDANTES) | Jor. | 0.002500 | $804.23 | $2.01 |
| APLANOS TALLER | MANO DE OBRA DE CALCULISTAS Y DIBUJANTES POR JORNADA DE TRABAJO | jor | 0.000250 | $1,330.86 | $0.33 |
| Suma de Mano de Obra | $8.46 | ||||
| Herramienta | |||||
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.015000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| GRUA | Grua de 20 ton. | HR | 0.006667 | $453.24 | $3.02 |
| AEQUIPO OXICORTE | EQUIPO DE CORTE OXIGENO-GAS | hora | 0.013880 | $10.10 | $0.14 |
| AAESMERILADORA | ESMERILADORA | hora | 0.028440 | $2.64 | $0.08 |
| ASOLDADORA | Soldadora Miller Mod. S64 | HR | 0.018310 | $16.12 | $0.30 |
| AEQUIPO PINTURA | EQUIPO DE PINTURA IPSA | hora | 0.010000 | $13.12 | $0.13 |
| Suma de Equipo | $3.66 | ||||
| Costo Directo | $24.87 |