| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OC-04 | COLADO SOBRE VIGAS DE FIERRO | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELECTRO | MALLA ELECTR. 6X6/6-6 | M2 | 0.205000 | $25.51 | $5.23 |
| Suma de Material | $5.23 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.025000 | $673.86 | $16.85 |
| Suma de Mano de Obra | $16.85 | ||||
| Auxiliar | |||||
| CONCRETO BOMB 250 | CONCRETO PREMEZCLADO FC=250 KG/CM2 BOMBEABLE | M3 | 0.150000 | $1,417.77 | $212.67 |
| Suma de Auxiliar | $212.67 | ||||
| Costo Directo | $234.74 |