| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PY-05 | REPELLADO SOBRE TABIQUE | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-003 | AGUA | M3 | 0.040000 | $12.40 | $0.50 |
| Suma de Material | $0.50 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.083333 | $717.71 | $59.81 |
| Suma de Mano de Obra | $59.81 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.040000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO C-C-A 1:1:3 | Mortero cemento cal arena 1:1:3 | M3 | 0.025000 | $655.06 | $16.38 |
| Suma de Auxiliar | $16.38 | ||||
| Costo Directo | $76.68 |