| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CARP14 | MM-06 BARRA-ESCRITORIO SIN CAJONERA DE 1.20 X 0.70 X 1.10 M. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CARPINTERIA 001 | MADERA DE PINO DE 1a. | PT | 62.100000 | $6.00 | $372.60 |
| CARPINTERIA 002 | TRIPLAY DE PINO DE 6 MM. | M2 | 9.200000 | $42.01 | $386.49 |
| CARPINTERIA 003 | CLAVO DE ALFILERILLO | KG | 0.920000 | $17.00 | $15.64 |
| CARPINTERIA-013 | PLASTICO LAMINADO RALP WILSON BLANCO MATE | M2 | 9.200000 | $125.00 | $1,150.00 |
| CARPINTERIA 004 | RESISTOL 850 | LT | 0.920000 | $54.00 | $49.68 |
| CARPINTERIA-004 | RESISTOL 5000 | LT | 2.300000 | $35.00 | $80.50 |
| CARPINTERIA 005 | LIJA PARA MADERA | PLIEGO | 1.380000 | $5.00 | $6.90 |
| CARPINERIA-005 | TRIPLAY DE 13 MM | M2 | 2.760000 | $90.00 | $248.40 |
| CARPINTERIA 007 | TORNILLO PARA MADERA | PZA | 11.500000 | $0.50 | $5.75 |
| CARPINTERIA 011 | BARNIZ SEMI-MATE | LT | 2.000000 | $58.00 | $116.00 |
| Suma de Material | $2,431.96 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 17 | (1 Of. Carpintero de banco + 1 Ayte) | Jor | 2.360000 | $582.00 | $1,373.52 |
| Suma de Mano de Obra | $1,373.52 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | (%)mo | 0.200000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $3,805.48 |