| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERR09 | H-18 AREA DE LAVADO 1.65 X 2.70MTS CON DOS HOJAS DE 0.825 X 2.70MTS CON PORTACANDADO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL ZP-150 | CAL. 20 | ML | 6.256800 | $15.30 | $95.73 |
| PINTURA-03 | PINTURA DE ESMALTE COMEX 100 | LT | 2.692800 | $58.00 | $156.18 |
| PINTURA-06 | THINNER | LT. | 1.584000 | $16.50 | $26.14 |
| PINTURA-05 | PRIMARIO ANTICORROSIVO | LT | 1.267200 | $29.00 | $36.75 |
| PERFIL 01-PUERTA | BIBEL PARA PUERTA | PZA | 4.000000 | $12.00 | $48.00 |
| PERFIL 03-PUERTA | PORTACANDADO | PZA | 1.000000 | $46.00 | $46.00 |
| PERFIL ZP-200 | CAL. 20 | ML | 7.167600 | $17.00 | $121.85 |
| PERFIL ZP-300 | CAL. 20 | ML | 1.663200 | $21.30 | $35.43 |
| PERFIL LAMINA | DE TABLERO ZTC 148 | M2 | 5.068800 | $48.00 | $243.30 |
| SOLDADURA E-6013 | SOLDADURA E-6013 | KG | 0.633600 | $21.20 | $13.43 |
| PERFIL 02-PUERTA | DISCO P/DESBASTE | PZA | 0.015840 | $38.00 | $0.60 |
| Suma de Material | $823.41 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1 OF. Herrero+1 AYUD.) | Jor | 1.675000 | $388.45 | $650.65 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 0.990000 | $521.54 | $516.32 |
| Suma de Mano de Obra | $1,166.98 | ||||
| Equipo | |||||
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 6.000000 | $6.75 | $40.50 |
| ESMERILADORA | ESMERILADORA | HR | 2.000000 | $19.29 | $38.58 |
| Suma de Equipo | $79.08 | ||||
| Costo Directo | $2,069.47 |