| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| DALA29-4 | DE 15 X 15 cms. DE SECCION CON CIMBRA EN LAS CARAS,ARMADO CON 4 VARILLAS DEL No. 3 (3/8") A.R. Y ESTRIBOS DEL No.2 (1/4"), GRADO ESTRUCTURAL A CADA 20 cm. (CADENA CON TRAZO CIRCULAR). (CASTILLO). INCLUYE ANCLAJE A FIRME, LOSA O CONTRATRABE. | M |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 398.16 | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.023180 | $705.12 | $16.34 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $5.50 | $0.55 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.070000 | $69.00 | $4.83 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.180000 | $10.00 | $1.80 |
| ACERO 03 | ACERO DEL # (3/) | KG | 2.450800 | $4.50 | $11.03 |
| ACERO-022 | ALAMBRON | KG | 0.687500 | $4.50 | $3.09 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.010000 | $5.00 | $0.05 |
| Suma de Material | $43.70 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Pe贸n) | Jor | 0.133330 | $372.73 | $49.70 |
| Suma de Mano de Obra | $49.70 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.23 | $1.52 |
| Suma de Equipo | $1.52 | ||||
| Costo Directo | $94.92 |