| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TUCOBRE04 | DE 19 MM. DE DIAMETRO NACOBRE O EQUIVALENTE TIPO "L" | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO CU T/L 19MM | TUBO CU T/L 19MM | ML | 6.000000 | $24.00 | $144.00 |
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.040000 | $51.40 | $2.06 |
| BROCHA 2" | BROCHA DE 2" | PZA | 0.033330 | $9.50 | $0.32 |
| THINER | THINER | LTO | 0.026250 | $14.50 | $0.38 |
| ESTOPA | ESTOPA | Kg. | 0.040000 | $25.00 | $1.00 |
| Suma de Material | $147.75 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.130000 | $647.77 | $84.21 |
| Suma de Mano de Obra | $84.21 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.025000 | $15.48 | $0.39 |
| Suma de Auxiliar | $0.39 | ||||
| Costo Directo | $232.35 |