| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| SOPM04 | . PARA 4 TUBOS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAQUETE SCI 3/8" | TAQUETE SCI 3/8" | PZA | 2.000000 | $4.50 | $9.00 |
| VARILLA ROSC. 3/8 | VARILLA ROSC. 3/8 | ML | 2.600000 | $9.80 | $25.48 |
| TUERCA GALV. 3/8" | TUERCA GALVANIZADA DE 3/8" | PZA | 2.000000 | $0.35 | $0.70 |
| ANGULO 3/16X1 1/2 | ANGULO DE 3/16 X 11/2" | ML | 1.000000 | $13.00 | $13.00 |
| PINTURA PRIMARIO | PINTURA PRIMARIO | LT | 0.028570 | $45.00 | $1.29 |
| BROCHA 2" | BROCHA DE 2" | PZA | 0.025000 | $9.50 | $0.24 |
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.028570 | $51.40 | $1.47 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 0.050000 | $25.00 | $1.25 |
| Suma de Material | $52.42 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.142860 | $647.77 | $92.54 |
| Suma de Mano de Obra | $92.54 | ||||
| Costo Directo | $144.96 |