| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PRET01 | P-3 DE ORILLA DE 1.70 m. DE ALTURA X 0.15 m. DE ANCHO. INCLUYENDO REPISON DE CONCRETO ARMADO DE 15 X 30CMS, CIMBRA, DESCIMBRA, ELABORACION DEL CONCRETO. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 398.16 | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.052000 | $705.12 | $36.67 |
| AGREGADO-021 | TABIQUE ROJO | PZA | 60.000000 | $0.86 | $51.60 |
| MORTERO 1:5 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.034000 | $607.42 | $20.65 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $5.00 | $6.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $5.50 | $0.55 |
| CIMBRA-011 | CHAFLAN DE 1" | ML | 2.000000 | $4.00 | $8.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.100000 | $69.00 | $6.90 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.180000 | $10.00 | $1.80 |
| ACERO 03 | ACERO DEL # (3/) | KG | 2.450800 | $4.50 | $11.03 |
| ACERO-022 | ALAMBRON | KG | 0.750000 | $4.50 | $3.38 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.030000 | $5.00 | $0.15 |
| Suma de Material | $146.72 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.400000 | $372.73 | $149.09 |
| Suma de Mano de Obra | $149.09 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.23 | $1.52 |
| Suma de Equipo | $1.52 | ||||
| Costo Directo | $297.34 |