| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 1-009 | PLANTILLA DE CONCRETO PREMEZCLADO DE RESISTENCIA NORMAL F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR. | m2 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.256000 | $5.61 | $1.44 |
| CONCRETO PRE F麓C=100 | CONCRETO PREMEZCLADO F'C = 100 KG/CM2 | m3 | 0.050000 | $759.11 | $37.96 |
| Suma de Material | $39.39 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBA脩IL + 1 AYUDANTE DE ALBA脩IL) | JOR | 0.044444 | $728.21 | $32.36 |
| Suma de Mano de Obra | $32.36 | ||||
| Costo Directo | $71.76 |