| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7.20-3-EXT | PINTURA DE ESMALTE EN ESTRUCTURA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA ESMALTE ACR | PINTURA DE ESMALTE ACRILICO | LT | 0.030000 | $78.00 | $2.34 |
| PRIMARIO ANTICORROSI | PRIMARIO ANTICORROSIVO | LT | 0.020000 | $56.00 | $1.12 |
| THINER | THINER | lt | 0.020000 | $12.00 | $0.24 |
| Suma de Material | $3.70 | ||||
| Mano de Obra | |||||
| CUADRILLA -44 | (1 OF. PINTORr + 2 AYUDANTES.) | JOR | 0.002600 | $1,033.73 | $2.69 |
| Suma de Mano de Obra | $2.69 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.002000 | $45.00 | $0.09 |
| Suma de Herramienta | $0.09 | ||||
| Equipo | |||||
| COMPRESOR | EQUIPO PARA APLICAR PINTURA EN FRANJAS (PINTA RAYAS) | HR | 0.000800 | $37.00 | $0.03 |
| Suma de Equipo | $0.03 | ||||
| Costo Directo | $6.51 |