| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A2-07 | PERFILADO VOLEADO DE ARISTAS VIVAS CON MORTERO CEMENTO ARENA 1:5, INCLUYE: MATERIALES Y MANO DE OBRA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-3 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 0.300000 | $8.00 | $2.40 |
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.020000 | $40.00 | $0.80 |
| Suma de Material | $3.20 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.037496 | $639.06 | $23.96 |
| Suma de Mano de Obra | $23.96 | ||||
| Herramienta | |||||
| ANDAMIOS | ANDAMIOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.003000 | $837.84 | $2.51 |
| Suma de Auxiliar | $2.51 | ||||
| Costo Directo | $29.68 |