| 10 | ARMEX 20X30/4 EN ESTRUCTURA PLANTA BAJA INCLUYE SUMINISTRO, CORTE, COLOCACION, TRASLAPES, DESPERDICIOS, FLETE Y ACARREOS. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| A1GAR060 | Armex 15 x 30-4 | m | 1.100000 | $14.33 | $15.76 |
| A1GAR060 | Armex 15 x 30-4 | m | 1.100000 | $14.33 | $15.76 |
| A1GAR060 | Armex 15 x 30-4 | m | 1.100000 | $14.33 | $15.76 |
| Suma de Material | $47.29 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | Jor | 0.016667 | $791.55 | $13.19 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | Jor | 0.016667 | $791.55 | $13.19 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | Jor | 0.016667 | $791.55 | $13.19 |
| Suma de Mano de Obra | $39.58 | ||||
| Costo Directo | $86.87 |