| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TOR-014-A. | CONCRETO PREMEZCLADO DE F'C = 300 KG/CM2 EN CONTRATRABES Y DADOS DE CIMENTACION, INCLUYE: MUESTREO, BOMBEO CON PLUMA, VACIADO, VIBRADO, CURADO, MANO DE OBRA, HERRAMIENTA Y EQUIPO (P.U.O.T.). | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C 300 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 300 KG/CM2, T.M.A. 3/4", | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| CONC.PREMEZ.F-C 300 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 300 KG/CM2, T.M.A. 3/4", | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| CONC.PREMEZ.F-C 300 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 300 KG/CM2, T.M.A. 3/4", | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| CONC.PREMEZ.F-C 300 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 300 KG/CM2, T.M.A. 3/4", | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| CONC.PREMEZ.F-C 300 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 300 KG/CM2, T.M.A. 3/4", | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| BOMBEO CON | BOMBEO DE CONCRETO PREMEZCLADO | M3 | 1.050000 | $135.00 | $141.75 |
| BOMBEO CON | BOMBEO DE CONCRETO PREMEZCLADO | M3 | 1.050000 | $135.00 | $141.75 |
| BOMBEO CON | BOMBEO DE CONCRETO PREMEZCLADO | M3 | 1.050000 | $135.00 | $141.75 |
| BOMBEO CON | BOMBEO DE CONCRETO PREMEZCLADO | M3 | 1.050000 | $135.00 | $141.75 |
| BOMBEO CON | BOMBEO DE CONCRETO PREMEZCLADO | M3 | 1.050000 | $135.00 | $141.75 |
| AGUA | ACARREO INTERNO | M3 | 0.095000 | $6.50 | $0.62 |
| AGUA | ACARREO INTERNO | M3 | 0.095000 | $6.50 | $0.62 |
| AGUA | ACARREO INTERNO | M3 | 0.095000 | $6.50 | $0.62 |
| AGUA | ACARREO INTERNO | M3 | 0.095000 | $6.50 | $0.62 |
| AGUA | ACARREO INTERNO | M3 | 0.095000 | $6.50 | $0.62 |
| Suma de Material | $5,961.84 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 13 | (1 OFICIAL ALBAÑIL + 5 PEONES). | JOR | 0.083333 | $1,656.74 | $138.06 |
| CUADRILLA NO. 13 | (1 OFICIAL ALBAÑIL + 5 PEONES). | JOR | 0.083333 | $1,656.74 | $138.06 |
| CUADRILLA NO. 13 | (1 OFICIAL ALBAÑIL + 5 PEONES). | JOR | 0.083333 | $1,656.74 | $138.06 |
| CUADRILLA NO. 13 | (1 OFICIAL ALBAÑIL + 5 PEONES). | JOR | 0.083333 | $1,656.74 | $138.06 |
| CUADRILLA NO. 13 | (1 OFICIAL ALBAÑIL + 5 PEONES). | JOR | 0.083333 | $1,656.74 | $138.06 |
| Suma de Mano de Obra | $690.31 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.189500 | $49.36 | $9.35 |
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.189500 | $49.36 | $9.35 |
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.189500 | $49.36 | $9.35 |
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.189500 | $49.36 | $9.35 |
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.189500 | $49.36 | $9.35 |
| Suma de Equipo | $46.77 | ||||
| Costo Directo | $6,698.91 |