| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TOREXT-08 | COLADO DE BASES DE CONCRETO FC=300 kg/cm2 PARA PODER DESPLANTAR COLUMNAS DE 1.00 X 1.00 X 0.10 MTS INCLUYE CIMBRA, COLADO, DESCIMBRA Y CURADO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA DE PINO | MADERA PINO 3a. | pt | 1.850000 | $7.00 | $12.95 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 1.250000 | $2.50 | $3.13 |
| CLAVO | CLAVO | KG | 0.150000 | $17.00 | $2.55 |
| DIESEL | DIESEL | LITRO | 0.500000 | $6.00 | $3.00 |
| Suma de Material | $21.63 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.166700 | $647.98 | $108.02 |
| Suma de Mano de Obra | $108.02 | ||||
| Costo Directo | $129.64 |