| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-MT-01 | SUMINISTRO E INSTALACION DE TRANSFORMADOR DE 225 KVA TRIFASICO 13200/7620 KV- 240/120V OPERACIÓN RADIAL CONEXIÓN Y T INCLUYE , MANIOBRAS CON GRUA, GABINETE Y PRUEBAS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRANSFORMADOR 3F | TRANSFORMADOR TRIFASICO DE 225 KVA | PZA | 1.000000 | $147,319.95 | $147,319.95 |
| INSERTO | PREMOLDEADO TIPO INSERTO BUSHING OCC 200 AMPS ELASTIMOLD. | PZA | 3.000000 | $522.00 | $1,566.00 |
| CODO 200 A P/CAL.1/0 | CONECTOR PREMOLDEADO TIPO CODO PARA 15 KV, 200 AMP., CAL.1/0 OPERACIÓN CON CARGA MCA. ELASTIMOLD CAT. 166LR-WX C/PROTOCOLO. | PZA | 3.000000 | $1,200.00 | $3,600.00 |
| ADAPTADOR 1/0 | ADAPTADOR DE PANTALLA PARA CABLE DE POTENCIA 1/0 AWG ELASTIMOLD O SIMILAR | PZA | 3.000000 | $324.80 | $974.40 |
| CONECTOR 4/0 AWG | CONECTOR TIPO C CAL. 4/0 - 4/0 AWG | PZA | 2.000000 | $73.50 | $147.00 |
| ZAPATA 2 OJILLO | ZAPATA DOBLE OJILLO 2-4/0 AWG. C/PROTOCOLO. | PZA | 1.000000 | $68.00 | $68.00 |
| ZAPATA 1 OJILLO | ZAPATA 1 OJILLO CAL. 2 AWG. | PZA | 4.000000 | $69.00 | $276.00 |
| VARILLA | VARILLA DE TIERRA DE 3 MTS | PZA | 3.000000 | $162.10 | $486.30 |
| TAPA FOFO | TAPA FOFO | PZA | 2.000000 | $1,798.00 | $3,596.00 |
| TUBERIA,CODOS,CONECT | TUBERIA,CODOS,CONECTORES | PZA | 1.000000 | $986.00 | $986.00 |
| MISCELANEOS | Miscelaneos | (%)mo | 0.050000 | $0.00 | $0.00 |
| GABINETE DONAS | Gabinetes para donas de medicion | pza | 1.000000 | $3,100.00 | $3,100.00 |
| PRUEBAS TRANSFORMAD | Pruebas a transformador | pza | 1.000000 | $2,050.00 | $2,050.00 |
| Suma de Material | $164,169.65 | ||||
| Mano de Obra | |||||
| CUADRILLA A.T. | CUDRILLA ALTA TENSION 1 LINIERO + 2 AYUDANTE | jor | 7.000000 | $1,116.31 | $7,814.17 |
| CUADRILLA ELECTRICIS | CUADRILLA No 84 ( 1 TEC. ELECTRICISTA + 2 AYTE. DE ELECTRICISTA ) | jor | 4.000000 | $680.48 | $2,721.92 |
| Suma de Mano de Obra | $10,536.09 | ||||
| Equipo | |||||
| HIAB CAMION-GRUA | CAMION GRUA DE TONELADAS CON TORRETA AMBAR DE SEÑALAMIENTO | HR | 3.000000 | $279.47 | $838.41 |
| Suma de Equipo | $838.41 | ||||
| Costo Directo | $175,544.15 |