| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OT.04 | FORJADO DE BASE PARA CALENTADOR DE 0.50X0.50 0.10 M. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CUADRILLA NO.09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.250000 | $749.14 | $187.29 |
| Suma de Mano de Obra | $187.29 | ||||
| Concepto | |||||
| E-01-01 | CIMBRA APARENTE EN COLUMNAS DE CONCRETO. | M2 | 1.000000 | $183.58 | $183.58 |
| E-01-02-3/4 | ACERO DE REFUERZO DE 3/4 EN COLUMNAS | KG | 5.000000 | $15.47 | $77.35 |
| E-01-03 | CONCRETO F'C=250 KG/CM2 EN COLUMNAS | M3 | 0.100000 | $1,386.19 | $138.62 |
| Suma de Concepto | $399.55 | ||||
| Costo Directo | $586.83 |