| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TOR-004. | ZAMPEADO SOBRE TALUD DE EXCAVACION PARA CIMENTACION CON MORTERO CEMENTO-ARENA PROPORCION 1 5, INCLUYE: MALLADE GALLINERO (P.U.O.T.) . | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | ACARREO INTERNO | M3 | 0.025000 | $6.50 | $0.16 |
| MALLA DE GALLINERO | Malla de gallinero | M2 | 1.100000 | $10.00 | $11.00 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 18 | KG | 0.010000 | $13.00 | $0.13 |
| Suma de Material | $11.29 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.050000 | $647.98 | $32.40 |
| Suma de Mano de Obra | $32.40 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE. 1:5 | MORTERO CEMENTO-ARENA 1:5 | M3 | 0.030000 | $637.94 | $19.14 |
| Suma de Auxiliar | $19.14 | ||||
| Costo Directo | $62.83 |