| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| H-5 | RAMPA DE CONCRETO PARA ACCESO A ESTACIONAMIENTO, CONCRETO F'C=200KG/CM2, ACABADO ESTRIADO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO-002 | CONCRETO PREMEZCLADO DE FC=200 KG/CM2 | M3 | 0.077000 | $905.00 | $69.69 |
| CIMBRA-002 | CIMBRAPLAY DE 16MM EN M2 | M2 | 0.200000 | $95.00 | $19.00 |
| CIMBRA-004 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 1.600000 | $10.83 | $17.33 |
| CIMBRA-003 | CLAVO | KG | 0.100000 | $13.05 | $1.31 |
| Suma de Material | $107.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.066667 | $749.14 | $49.94 |
| Suma de Mano de Obra | $49.94 | ||||
| Equipo | |||||
| VIBRADORCONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.700000 | $22.22 | $15.55 |
| Suma de Equipo | $15.55 | ||||
| Costo Directo | $172.81 |