| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM 02.10 | FIRME DE CONCRETO ARMADO DE 10 CMS DE ESPESOR F`c=200 KG/CM2 Y ARMADO CON MALLA ELECTROSOLDADA 6-6/6-6, ACABADO PULIDO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALAMBRE RECOC 18 | ALAMBRE RECOCIDO # 18 | KG | 0.089280 | $14.87 | $1.33 |
| ACES-003 | Mallas electrosoldadas 6X6-6/6. | m2 | 1.200000 | $23.75 | $28.50 |
| CONC.PREMEZ.F´C=300 | Concreto Premezclado F'c=300 Kg/cm2 A.M. 3/4" rev 13-14 | M3 | 0.110000 | $730.00 | $80.30 |
| REVENIMIENTO | REVENIMIENTO DE CONCRETO 14 Y 18 | M3 | 0.110000 | $90.00 | $9.90 |
| AGUA | Agua potable | M3 | 0.012500 | $40.00 | $0.50 |
| POLIN 3.5" X 3.5" | MADERA DE PINO DE 3A. EN POLIN DE 3.5" X 3.5" | PT | 1.500000 | $7.50 | $11.25 |
| BARROTE 1.5" X 3.5" | MADERA DE PINO DE 3A. EN BARROTE DE 1.5" X 3.5" | PT | 1.200000 | $5.60 | $6.72 |
| CLAVOS | VARIAS MEDIDAS NORMAL | KG | 0.300000 | $17.50 | $5.25 |
| DIESEL | diesel pemex | Lt | 0.580000 | $6.00 | $3.48 |
| Suma de Material | $147.23 | ||||
| Mano de Obra | |||||
| CUAD 18 | Cuadrilla No. 18 ( 1 Of. Fierrero + 1Ayudante). | jor | 0.008333 | $794.60 | $6.62 |
| CUAD 05 | ( 1 ALBAÑIL + 5 PEONES ) | jor | 0.020000 | $2,073.42 | $41.47 |
| CUAD 11 | (1 Of. Carpintero O.N. + 1Ayte). | jor | 0.012500 | $794.60 | $9.93 |
| Suma de Mano de Obra | $58.02 | ||||
| Equipo | |||||
| BOMBA PLUMA | Bomba pluma para concreto con diámetro hasta 4" (102mm) | M3 | 0.110000 | $90.00 | $9.90 |
| VIBRADOR | Vibrador para concreto Mot. Kohler 4 H.Con operador. | HR | 0.075000 | $53.08 | $3.98 |
| Suma de Equipo | $13.88 | ||||
| Costo Directo | $219.13 |