| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.II.9 | SUMINISTRO, HABILITADO, FABRICACION Y MONTAJE DE CONTRAFLAMBEOS Y TENSORES A BASE DE REDONDO A-36; INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-ACERO EST14 | REDONDO DIF. MEDIDAS | kg | 1.085000 | $12.00 | $13.02 |
| OC-COMB5 | GAS P/ CORTES | kg | 0.009000 | $8.70 | $0.08 |
| OC-COMB3 | OXIGENO | m3 | 0.013000 | $19.00 | $0.25 |
| OC-SOLD | SOLDADURA E 7018 | kg | 0.014440 | $45.00 | $0.65 |
| OC-DISCO | DISCO ABRASIVO | pza | 0.002200 | $45.00 | $0.10 |
| OC-ACERO EST9 | CUERDA | pza | 0.962570 | $5.61 | $5.40 |
| OC-ACERO EST13 | TUERCA 3/4" | pza | 0.976000 | $5.00 | $4.88 |
| OC-ACERO EST8 | ARANDELA 3/4" | pza | 1.000000 | $1.80 | $1.80 |
| Suma de Material | $26.17 | ||||
| Mano de Obra | |||||
| OC-CUA22 | Cuadrilla (1 Pailero + 1 Ayudante) | jor | 0.002260 | $891.99 | $2.02 |
| OC-CUA23 | Cuadrilla (1 Soldador + 1 Ayudante) | jor | 0.001740 | $868.74 | $1.51 |
| OC-CUA24 | Cuadrilla para estructura (1 Montador + 4 Ayudante) | jor | 0.001710 | $1,758.64 | $3.01 |
| Suma de Mano de Obra | $6.53 | ||||
| Herramienta | |||||
| OC-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.006969 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OC-EQUI26 | Equipo de corte de oxi-butano | hora | 0.015060 | $8.63 | $0.13 |
| OC-EQUI30 | Esmeriladora con plato cubre astilla, modelo 1752 potencia 2,000 w a 6,500, marca Bosch. | hora | 0.028440 | $2.64 | $0.08 |
| OC-EQUI33 | Soldadora Miller Mod. S64 | hora | 0.014450 | $9.69 | $0.14 |
| OC-EQUI31 | Grua de 20 ton. | hora | 0.001600 | $494.13 | $0.79 |
| Suma de Equipo | $1.14 | ||||
| Contrato | |||||
| I.II.9_SC | Subcontrato de I.II.9 | KG | 1.000000 | $3.06 | $3.06 |
| Suma de Contrato | $3.06 | ||||
| Costo Directo | $36.90 |