| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E-01 | SUMINISTRO E INSTALACION DE TUBO CONDUIT DE P.V.C. SERVICIO PESADO DE 19 MM DE ø, MCA. DURALON. INCLUYE: MATERIAL, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBCPVCTP19 | TUBO CONDUIT PVC TIPO PESADO 19MM | PZA | 0.336667 | $14.64 | $4.93 |
| CODOCPVCTP19 | CODO CONDUIT PVC TIPO PESADO DE 19MM | PZA | 0.050000 | $3.96 | $0.20 |
| PEGTANGITROS500 | PEGAMENTO TANGIT ROSADO , BOTE DE 500 ML | PZA | 0.010000 | $188.48 | $1.88 |
| LIJAESMERILFINA | LIJA DE ESMERIL FINA | PZA | 0.035000 | $14.50 | $0.51 |
| LIMPIADOR P/PVC | LIMPIADOR PARA TUBO DE PVC DE 450ML | BOTE | 0.025000 | $38.00 | $0.95 |
| ESTOPA | ESTOPA | KG | 0.015000 | $18.00 | $0.27 |
| SEGUETAD/STAN | SEGUETA DIENTE STANDARD | PZA | 0.015000 | $8.50 | $0.13 |
| Suma de Material | $8.87 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 02 | Cuadrilla de electricista ( Electricista + ayudante) | Jor | 0.012900 | $1,110.57 | $14.33 |
| Suma de Mano de Obra | $14.33 | ||||
| Costo Directo | $23.19 |