| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 10 | SUMINISTRO Y HECHURA DE TRABE DE LIGA TL-A CON ARMADO DE ACERO DE REFUERZO, CONCRETO, VACIADO, CIMBRA DESCIMBRA,RELLENO, HERRAM., M.O., LIMPIEZA DE 脕REA DE TRABAJO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCI脫N (DE ACUERDO A PLANOS ESTRUCTURALES ANEXOS) | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| CONCRETO PRE 250 | CONCRETO PREMEZCLADO F'C=250 KG/CM2 | M3 | 0.090000 | $1,167.63 | $105.09 |
| RELLENO | RELLENO CON MATERIAL PRODUCTO DE EXCAVACION | M3 | 1.970000 | $43.48 | $85.66 |
| Suma de Auxiliar | $190.74 | ||||
| Concepto | |||||
| CE-03-03 | ACERO DE REFUERZO DEL No. 3 AL 5 EN CIMENTACION | TON | 0.012300 | $14,773.76 | $181.72 |
| CE-02-01 | CIMBRA COMUN | M2 | 0.700000 | $100.34 | $70.24 |
| Suma de Concepto | $251.96 | ||||
| Costo Directo | $442.70 |