| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MT11 | Registro electrico media tension Norma CFE | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO | ACERO REF.VAR.DIAM. | kg | 61.000000 | $10.14 | $618.54 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO CAL. 16 | Kg | 0.660000 | $14.80 | $9.77 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | m2 | 14.000000 | $85.50 | $1,197.00 |
| CIMBRA-02 | CLAVO | Kg. | 1.500000 | $16.50 | $24.75 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 4.000000 | $5.61 | $22.44 |
| ACEITE DORADO | ACEITE DORADO NORMAL PEMEX | LT | 2.000000 | $30.00 | $60.00 |
| CONCRETO PRE-04 | CONCRETO PREMEZCLADO DE F'C= 200 KG/CM2 | M3 | 0.800000 | $950.00 | $760.00 |
| Suma de Material | $2,692.50 | ||||
| Mano de Obra | |||||
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.300000 | $230.27 | $69.08 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 4.000000 | $693.85 | $2,775.40 |
| Suma de Mano de Obra | $2,844.48 | ||||
| Equipo | |||||
| API-VIBRADORCONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 1.000000 | $21.95 | $21.95 |
| Suma de Equipo | $21.95 | ||||
| Costo Directo | $5,558.93 |