| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| FIRM-01 | FIRME DE CONCRETO PREMEZCLADO F´C= 200 KG/CM2, CLASE-1, DE 10 CMS DE ESPESOR, REFORZADA CON MALLA 6X6/8-8 INCLUYE: CELOTEX, CIMBRA METALICA, ACABADO CEPILLADO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-MALLA2 | MALLA ELECTROSOLDADA 6-6 8/8 | m2 | 1.030000 | $25.00 | $25.75 |
| OC-MALLA2 | MALLA ELECTROSOLDADA 6-6 8/8 | m2 | 1.030000 | $25.00 | $25.75 |
| OC-MALLA2 | MALLA ELECTROSOLDADA 6-6 8/8 | m2 | 1.030000 | $25.00 | $25.75 |
| OC-FESTER5 | DESMOLDANTE SEPAROL DE SIKA EN LTS | lt | 0.083333 | $36.50 | $3.04 |
| OC-FESTER5 | DESMOLDANTE SEPAROL DE SIKA EN LTS | lt | 0.083333 | $36.50 | $3.04 |
| OC-FESTER5 | DESMOLDANTE SEPAROL DE SIKA EN LTS | lt | 0.083333 | $36.50 | $3.04 |
| OC-ACERO REF5 | ALAMBRE RECOCIDO | kg | 0.050000 | $14.90 | $0.75 |
| OC-ACERO REF5 | ALAMBRE RECOCIDO | kg | 0.050000 | $14.90 | $0.75 |
| OC-ACERO REF5 | ALAMBRE RECOCIDO | kg | 0.050000 | $14.90 | $0.75 |
| OC-MAD6 | POLIN MADERA DE PINO 4"x4"x8' | pt | 0.250000 | $7.00 | $1.75 |
| OC-MAD6 | POLIN MADERA DE PINO 4"x4"x8' | pt | 0.250000 | $7.00 | $1.75 |
| OC-MAD6 | POLIN MADERA DE PINO 4"x4"x8' | pt | 0.250000 | $7.00 | $1.75 |
| OC-ACERO REF1 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | ton | 0.000100 | $8,500.00 | $0.85 |
| OC-ACERO REF1 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | ton | 0.000100 | $8,500.00 | $0.85 |
| OC-ACERO REF1 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | ton | 0.000100 | $8,500.00 | $0.85 |
| OC-CLAVO | CLAVO DIFERENTES MEDIDAS | kg | 0.001000 | $15.00 | $0.02 |
| OC-CLAVO | CLAVO DIFERENTES MEDIDAS | kg | 0.001000 | $15.00 | $0.02 |
| OC-CLAVO | CLAVO DIFERENTES MEDIDAS | kg | 0.001000 | $15.00 | $0.02 |
| Suma de Material | $96.45 | ||||
| Mano de Obra | |||||
| OC-CUA30 | Cuadrilla (1 Albañil + 1 Ayudante) | jor | 0.047619 | $841.89 | $40.09 |
| OC-CUA30 | Cuadrilla (1 Albañil + 1 Ayudante) | jor | 0.047619 | $841.89 | $40.09 |
| OC-CUA30 | Cuadrilla (1 Albañil + 1 Ayudante) | jor | 0.047619 | $841.89 | $40.09 |
| Suma de Mano de Obra | $120.27 | ||||
| Equipo | |||||
| OC-EQUI34 | ALLANADORA DOBLE NO TRALAPABLE DE 36" | hora | 0.025000 | $182.48 | $4.56 |
| OC-EQUI34 | ALLANADORA DOBLE NO TRALAPABLE DE 36" | hora | 0.025000 | $182.48 | $4.56 |
| OC-EQUI34 | ALLANADORA DOBLE NO TRALAPABLE DE 36" | hora | 0.025000 | $182.48 | $4.56 |
| Suma de Equipo | $13.69 | ||||
| Auxiliar | |||||
| OC-AUX8 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN CIMENTACION. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.110000 | $1,004.70 | $110.52 |
| OC-AUX8 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN CIMENTACION. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.110000 | $1,004.70 | $110.52 |
| OC-AUX8 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN CIMENTACION. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 | 0.110000 | $1,004.70 | $110.52 |
| Suma de Auxiliar | $331.55 | ||||
| Costo Directo | $561.96 |