| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 113 | TRAZO Y NIVELACION DEL TERRENO NATURAL INCLUYE: MAQUINARIA, HERRAMIENTA, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION (DE ACUERDO A NIVELES DE PROYECTO) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.000700 | $828.86 | $0.58 |
| CALHIDRA | CALHIDRA EN SACO | ton | 0.000100 | $900.00 | $0.09 |
| MADERA DE PINO 3A | madera para estacas | pt | 0.002000 | $4.34 | $0.01 |
| Suma de Material | $0.68 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 08 | (1 topografo + 2 cadeneros) | JOR | 0.005000 | $1,350.34 | $6.75 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.025000 | $230.27 | $5.76 |
| Suma de Mano de Obra | $12.51 | ||||
| Equipo | |||||
| ATRANSITO | TRANSITO CON TRIPIE Y PLOMADA OPTICA | hora | 0.010000 | $18.86 | $0.19 |
| ANIVEL CON TRIPIE | NIVEL CON TRIPIE | HR | 0.075000 | $29.65 | $2.22 |
| Suma de Equipo | $2.41 | ||||
| Costo Directo | $15.60 |