| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.I.5 | SUMINISTRO, HABILITADO, FABRICACION Y MONTAJE DE ESTRUCTURA METALICA A BASE DE VIGA IR DE 18" X 89.10 KG/ML, 24" X 155 KG/ML, 16" X 74.4 KG/ML, 10" X 32.9 KG/ML, 12" X 52.2 KG/ML; INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OC-ACERO EST4 | IR DIF. MEDIDAS | kg | 1.085000 | $11.30 | $12.26 |
| OC-COMB5 | GAS P/ CORTES | kg | 0.009000 | $8.70 | $0.08 |
| OC-COMB3 | OXIGENO | m3 | 0.013000 | $19.00 | $0.25 |
| OC-SOLD | SOLDADURA E 7018 | kg | 0.020000 | $45.00 | $0.90 |
| OC-DISCO | DISCO ABRASIVO | pza | 0.002200 | $45.00 | $0.10 |
| Suma de Material | $13.58 | ||||
| Mano de Obra | |||||
| OC-CUA22 | Cuadrilla (1 Pailero + 1 Ayudante) | jor | 0.002260 | $891.99 | $2.02 |
| OC-CUA23 | Cuadrilla (1 Soldador + 1 Ayudante) | jor | 0.001740 | $868.74 | $1.51 |
| OC-CUA24 | Cuadrilla para estructura (1 Montador + 4 Ayudante) | jor | 0.001730 | $1,758.64 | $3.04 |
| Suma de Mano de Obra | $6.57 | ||||
| Herramienta | |||||
| OC-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.006969 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OC-EQUI26 | Equipo de corte de oxi-butano | hora | 0.015060 | $8.63 | $0.13 |
| OC-EQUI30 | Esmeriladora con plato cubre astilla, modelo 1752 potencia 2,000 w a 6,500, marca Bosch. | hora | 0.028440 | $2.64 | $0.08 |
| OC-EQUI33 | Soldadora Miller Mod. S64 | hora | 0.014450 | $9.69 | $0.14 |
| OC-EQUI31 | Grua de 20 ton. | hora | 0.001620 | $494.13 | $0.80 |
| Suma de Equipo | $1.15 | ||||
| Contrato | |||||
| I.I.5_SC | Subcontrato de I.I.5 | KG | 1.000000 | $1.93 | $1.93 |
| Suma de Contrato | $1.93 | ||||
| Costo Directo | $23.23 |