| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 8 | SUMINISTRO Y HECHURA DE ZAPATAS CORRIDAS ZC2 CON ARMADO DE ACERO DE REFUERZO, CONCRETO, VACIADO, CIMBRA DESCIMBRA,RELLENO, HERRAM., M.O., LIMPIEZA DE 脕REA DE TRABAJO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCI脫N (DE ACUERDO A PLANOS ESTRUCTURALES ANEXOS) | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| RELLENO | RELLENO CON MATERIAL PRODUCTO DE EXCAVACION | M3 | 3.140000 | $43.48 | $136.53 |
| CONCRETO PRE 250 | CONCRETO PREMEZCLADO F'C=250 KG/CM2 | M3 | 0.260000 | $1,167.63 | $303.58 |
| Suma de Auxiliar | $440.11 | ||||
| Concepto | |||||
| CE-03-03 | ACERO DE REFUERZO DEL No. 3 AL 5 EN CIMENTACION | TON | 0.040700 | $14,773.76 | $601.29 |
| CE-02-01 | CIMBRA COMUN | M2 | 1.400000 | $100.34 | $140.48 |
| Suma de Concepto | $741.77 | ||||
| Costo Directo | $1,181.88 |