| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.35.7 | SUMINISTRO E INSTALACION DE REDUCCION METR-INGL 160-3" MM C-7 CEM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0768393 | REDUC. HID METR-METR. CAMP. 160-100 MM TC 7 | PZ | 1.000000 | $302.78 | $302.78 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 0.264000 | $24.80 | $6.55 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.160000 | $8.82 | $1.41 |
| Suma de Material | $310.74 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.029360 | $749.35 | $22.00 |
| Suma de Mano de Obra | $22.00 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.013470 | $164.54 | $2.22 |
| Suma de Equipo | $2.22 | ||||
| Costo Directo | $334.96 |