| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7.1 | SUMINISTRO E INSTALACION DE CAÑON 2" NELSON F-100, B-0.85" O SIMILAR | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1323130N | CANON NELSON MOD.F-100 CC BOQ. .85" RM 50 MM | PZ | 1.000000 | $13,319.08 | $13,319.08 |
| Suma de Material | $13,319.08 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.004799 | $749.35 | $3.60 |
| Suma de Mano de Obra | $3.60 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.002259 | $164.54 | $0.37 |
| Suma de Equipo | $0.37 | ||||
| Costo Directo | $13,323.05 |