| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.4.5 | SUMINISTRO E INSTALACION DE TUBO HID PVC ING. DE 4" R-41 C/C | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0401129 | TUBO HID S/I RD-41 100 MM 6M C/C | MT | 1.000000 | $64.65 | $64.65 |
| 9700142 | LUBRICANTE REXOLIT LATA500 GRS. | PZ | 0.002000 | $11.55 | $0.02 |
| Suma de Material | $64.67 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.013190 | $749.35 | $9.88 |
| Suma de Mano de Obra | $9.88 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.006140 | $164.54 | $1.01 |
| AMAIN-106 | Remolque cama baja | hora | 0.006140 | $4.67 | $0.03 |
| Suma de Equipo | $1.04 | ||||
| Costo Directo | $75.60 |