| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.2.5 | SUMINISTRO E INSTALACION DE TUBO HID PVC MTR DE 160 MM C-7 C/C | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0750217 | TUBO HID S/M C- 7 160 MM 6M C/C | MT | 1.000000 | $130.37 | $130.37 |
| 9700142 | LUBRICANTE REXOLIT LATA500 GRS. | PZ | 0.002167 | $11.55 | $0.03 |
| Suma de Material | $130.40 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.021071 | $749.35 | $15.79 |
| Suma de Mano de Obra | $15.79 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.009850 | $164.54 | $1.62 |
| AMAIN-106 | Remolque cama baja | hora | 0.009786 | $4.67 | $0.05 |
| Suma de Equipo | $1.67 | ||||
| Costo Directo | $147.85 |