| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESCALON3 | FORJADO DE ESCALON FIJO EN TRIANGULO DE 0.70X0.50 INCLUYE RELLENO DE 0.40 M DE ALTURA MUROS PERIMETRALES DE TABIQUE Y FORJADO FIRME MARTELINADO ARMADO CON MALLA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 0.210000 | $15.74 | $3.31 |
| SIKADUR | SIKADUR | KG | 0.056000 | $106.46 | $5.96 |
| TABIQUE | TABIQUE ROJO RECOCIDO | PZA | 54.000000 | $1.20 | $64.80 |
| RELLENO LIMPIO | RELLENO LIMPIO | M3 | 0.070000 | $30.00 | $2.10 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.220000 | $5.61 | $1.23 |
| Suma de Material | $77.40 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones) | jor | 0.100000 | $1,935.14 | $193.51 |
| Suma de Mano de Obra | $193.51 | ||||
| Auxiliar | |||||
| MARTELINADO | MARTELINADO | M2 | 0.175000 | $292.42 | $51.17 |
| Suma de Auxiliar | $51.17 | ||||
| Costo Directo | $322.09 |