| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| DESCANSO2 | FORJADO DE DESCANSO ARMADO CON MALLA ELECTROSOLDADA ACABADO MARTELINADO NARIZ ACABADO BOLEADO CON PVC 2"POR LOS CUATRO LADOS DE 1.40 X 2.36 MTS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO PVC SAN 50MM | TUBO DE PVC SANITARIO EXTREMO LISO DE NORMA DE 51 MM DE DIAMETRO MARCA REXOLIT PARA CEMENTAR | ML | 7.520000 | $21.00 | $157.92 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 4.217000 | $15.74 | $66.38 |
| SIKADUR | SIKADUR | KG | 0.900000 | $106.46 | $95.81 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.583000 | $5.61 | $3.27 |
| Suma de Material | $323.38 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones) | jor | 0.125000 | $1,935.14 | $241.89 |
| Suma de Mano de Obra | $241.89 | ||||
| Auxiliar | |||||
| MARTELINADO | MARTELINADO | M2 | 3.514200 | $292.42 | $1,027.62 |
| Suma de Auxiliar | $1,027.62 | ||||
| Costo Directo | $1,592.90 |