| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EXTRA10 | FABRICACION DE TRABE DE CONCRETO F`C=200KG/CM2, ARMADA CON 4 VAR. No. 4 Y ESTRIBOS DE No. 2 A CADA 20 CM. EN ZONA ROCOSA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | ACERO DEL # 3 ( 1/2") AL # 6 (3/4) | KG | 6.380000 | $9.20 | $58.70 |
| ACERO ALAMBRE | ALAMBRE REC. | KG | 0.120000 | $13.00 | $1.56 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.300000 | $67.00 | $20.10 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.200000 | $5.50 | $1.10 |
| COMBUSTIBLE 05 | DIESEL | LT | 1.200000 | $4.80 | $5.76 |
| CIMBRA-05 | MOÑO PARA CIMBRA | PZA | 2.500000 | $6.80 | $17.00 |
| Suma de Material | $104.22 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.044000 | $393.73 | $17.32 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.150000 | $393.73 | $59.06 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.025000 | $378.04 | $9.45 |
| Suma de Mano de Obra | $85.83 | ||||
| Auxiliar | |||||
| CONCRETO HECHO 200 | CONCRETO HECHO EN OBRA DE 200 KG /CM2 | M3 | 0.120000 | $892.86 | $107.14 |
| Suma de Auxiliar | $107.14 | ||||
| Costo Directo | $297.19 |