| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| V.030 | TRABE DE CONCRETO F`C=250 KG/CM2. ARMADA CON 4 VARILLAS No. 5 Y ANILLOS DEL No.3 @ 20 CM.CIMBRA APARENTE Y CHAFLANES EN ARISTAS DE 1/2", CIMBRA APARENTE, MEDIDAS 22.5 X 40 CM. INCLUYE : MATERIALES EN SITIO DE LA OBRA, CIMBRA, DECIMBRA, MANO DE OBRA, ANDAMIOS, ACARREOS, FLETES, DESPERDICIOS, TRASLAPES, DOBLECES, ANCLAJES, CHAFLANES, HERRAMIENTA, EQUIPO, COLADO, ACABADO.(P.U.O.T.). | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO DE 250 KG/CM2, INCLUYE: REVENIMIENTO 12-14. | m3 | 0.090000 | $800.00 | $72.00 |
| ACERO | ACERO REF.VAR.DIAM. | kg | 9.110000 | $5.70 | $51.93 |
| Suma de Material | $123.93 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.200000 | $45.00 | $9.00 |
| Suma de Herramienta | $9.00 | ||||
| Concepto | |||||
| III.009 | CIMBRA APARENTE CON MADERA DE PINO Y TRIPLAY EN LOSAS , TRABES Y FALDONES PLANTA BAJA INCLUYE: MANO DE OBRA( CIMBRA Y DECIMBRA ), ACARREOS A DOS ESTACIONES MAXIMO,ELEVACION DE MATERIALES, ALAMBRE DE AMARRE RECOCIDO DEL No. 16,CHAFLANES EN GOTEROS Y ARISTAS, CLAVO DIFERENTES MEDIDAS, DESMOLDANTE, HERRAMIENTA, EQUIPO, FLETES, DESPERDICIOS, CORTES. ( P.U.O.T.). | M2 | 0.800000 | $89.31 | $71.45 |
| Suma de Concepto | $71.45 | ||||
| Costo Directo | $204.38 |