| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| XIII.2 | SALIDA PARA DATOS INCLUYE :TUBO CONDUIT DE PVC TIPO PESADO 25 MM DE DIAM,CAJA PVC ,MATERIALES, MANO DE OBRA ,HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA INSTALACION (P.U.O.T). | SAL |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C.PVC TP 19MM | TUBO C.PVC TP 19MM | ML | 3.636360 | $5.72 | $20.80 |
| TUBO C.PVC TP 25 MM | TUBO C.PVC TP 25 MM | ML | 9.090910 | $7.27 | $66.09 |
| CURVA PVC 19 MM | CURVA PVC 19 MM | PZA | 1.363640 | $5.72 | $7.80 |
| CURVA PVC 25 MM. | CURVA PVC 25 MM. | PZA | 1.363640 | $9.09 | $12.40 |
| CURVA PVC 32 MM | CURVA PVC 32 MM | PZA | 1.363640 | $24.64 | $33.60 |
| CONDULET 25MM MOD OT | CAJA OVAL ROSCADA, CON TAPA LIBRE DE COBRE MOD. "OT" DE 25 MM. CALIDAD RAWELT. | PZA | 2.500000 | $20.00 | $50.00 |
| CONEC. PVC TP 19 MM | CONEC. PVC TP 19 MM | PZA | 1.818180 | $4.78 | $8.69 |
| CONEC. PVC TP 25 MM | CONEC. PVC TP 25 MM | PZA | 1.818180 | $6.35 | $11.55 |
| CONEC. PVC TP 32 MM | CONEC. PVC TP 32 MM | PZA | 1.818180 | $8.88 | $16.15 |
| CAJA GALV. 19 MM | CAJA GALV. 19 MM | PZA | 1.636360 | $3.78 | $6.19 |
| CONDULET25MMGRTZ | SERIE GR CON TAPA LIBRE DE COBRE MOD. GRTZ DE 25 MM. CALIDAD RAWELT. | PZA | 0.500000 | $208.00 | $104.00 |
| CAJA GALV. 25 MM | CAJA GALV. 25 MM | PZA | 1.636360 | $16.91 | $27.67 |
| CAJA GALV. 32 MM | CAJA GALV. 32 MM | PZA | 1.363640 | $52.47 | $71.55 |
| CAJA 0.40 X 0.40 CM | CAJA 0.40 X 0.40 CM | PZA | 1.000000 | $350.00 | $350.00 |
| TUBO C.PVC TP 32 MM | TUBO C.PVC TP 32 MM | ML | 7.272730 | $9.82 | $71.42 |
| GUIA ALAMBRE 12 | ALAMBRE PARA GUIA | ML | 10.909090 | $1.80 | $19.64 |
| PEGAM. TANGIT 500 ML | PEGAM. TANGIT 500 ML | PZA | 0.818180 | $98.00 | $80.18 |
| LIMPIADOR P/PVC | LIMPIADOR PVC 250ML | BOTE | 0.454540 | $27.00 | $12.27 |
| ESTOPA | ESTOPA | KG | 0.181820 | $13.20 | $2.40 |
| SEGUETA | SEGUETA | PZA | 0.181820 | $8.50 | $1.55 |
| SOPORTERIA TEL | TELEFONIA | PZA | 0.200000 | $1,856.00 | $371.20 |
| Suma de Material | $1,345.13 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 32 IN | Cuadrilla de Plomeros | jor | 1.120000 | $712.87 | $798.41 |
| Suma de Mano de Obra | $798.41 | ||||
| Auxiliar | |||||
| TORRE HIDRAULICA | MODULO DE 5.5 MTS PARA INSTALACIONES, CON LLANTAS | R/D | 0.800000 | $65.00 | $52.00 |
| Suma de Auxiliar | $52.00 | ||||
| Costo Directo | $2,195.54 |