| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| XJ.19 | a).- CAL. 1/0 AWG. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CABLE XLP 1/0 AL15KV | CABLE XLP 1/0 AL15KV LATINCASA | ML | 1.100000 | $85.00 | $93.50 |
| CINTA 33 SCOTCH- | CINTA DE AISLAR No. 33 MARCA SUPER 3-M | PZA | 0.150000 | $68.00 | $10.20 |
| Suma de Material | $103.70 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.010000 | $615.95 | $6.16 |
| CUADRILLA ALTA TENS. | Cuadrilla Electrica Alta Tension | jor | 0.030000 | $1,780.65 | $53.42 |
| Suma de Mano de Obra | $59.58 | ||||
| Costo Directo | $163.28 |