| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| V.018 | FIRME DE CONCRETO SIMPLE F`C= 150 KG/CM2. DE 10.00 CM. DE ESPESOR, ACABADO CON CEPILLO DE MADERA INCLUYE : CIMBRA CON MADERA O METALICA, HUMEDECER SUPERFICIE ANTES DEL COLADO, EXTENDIDO, VIBRADO, ACARREOS A UNA DISTANCIA MAXIMA DE DOS ESTACIONES, DESPERDICIOS, HERRAMIENTA, EQUIPO, CURADO CON MEMBRANA COLOR ROJO APLICADA CON RODILLO O ASPERSOR. ( P.U.O.T.). | M2. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.105000 | $775.81 | $81.46 |
| AGUA | AGUA | m3 | 0.067000 | $35.00 | $2.35 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.600000 | $5.90 | $9.44 |
| CLAVO | CLAVO | KG | 0.040000 | $13.74 | $0.55 |
| CURACRETO | CURACRETO | LT | 0.300000 | $9.90 | $2.97 |
| Suma de Material | $96.76 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.080000 | $536.61 | $42.93 |
| Suma de Mano de Obra | $42.93 | ||||
| Costo Directo | $139.69 |