| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| VIII.013 | ESTRUCTURA PARA PASARELA ( SEGUN PLANOS ), A BASE DE TUBO Y PERFILES DE ACERO EN EL AREA DE CONTROL DE ACCESO Y SALIDA DE VEHICULOS, INCLUYE : MATERIALES, GALVANIZADO EN CALIENTE, FABRICACION EN TALLER, ACARREOS, FLETES, UNA MANO DE ENLACE EPOXICO Y DOS MANOS DE PINTURA DE POLIURETANO ( 8 MILLS. ), MANO DE OBRA, RESANES EN CAMPO CON GALVANIZADO EN FRIO, MONTAJE, HERRAMIENTA, EQUIPO.( P.U.O.T.). | M2. |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL DE ACERO | PERFIL DE ACERO | KG | 0.000000 | $15.00 | $0.00 |
| PINTURA | PINTURA DE POLIURETANO COLOR AMARILLO Y NEGRO | KG | 0.000000 | $2.50 | $0.00 |
| PINTURA 1 | PINTURA DE ENLACE EPOXICO | KG | 0.000000 | $3.50 | $0.00 |
| TUBO NEGRO 1 | TUBO NEGRO 2" CED 40 | ML | 0.000000 | $56.00 | $0.00 |
| GALVAN. EN CAL. | GALVANIZADO EN CALIENTE | KG | 0.000000 | $3.45 | $0.00 |
| TUBO NEGRO 3 | TUBO NEGRO DE 4" GALV. | ML | 0.000000 | $225.00 | $0.00 |
| TUBO NEGRO | TUBO NEGRO DE 6" CED. 40 | ML | 0.000000 | $318.00 | $0.00 |
| ENERGIA ELECTRICA | ENERGIA ELECTRICA | KW | 1.600000 | $0.85 | $1.36 |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 0.200000 | $30.28 | $6.06 |
| OXIGENO | OXIGENO | M3 | 0.160000 | $38.50 | $6.16 |
| GAS P/CORTES | GAS P/ CORTES | KG | 0.240000 | $3.96 | $0.95 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.032000 | $31.25 | $1.00 |
| Suma de Material | $15.53 | ||||
| Mano de Obra | |||||
| CUADRILLA 04 | CUADRILLA DE PAILERIA(1 OFICIAL PAILERO + 1 OFICIAL SOLDADOR + 2 AYUDANTES) | Jor. | 0.020000 | $1,217.60 | $24.35 |
| Suma de Mano de Obra | $24.35 | ||||
| Equipo | |||||
| API-MAQ-SOLDAR-EST | SOLDADORA MILLER DIMENSION MOD. 652 | hora | 0.320000 | $10.80 | $3.46 |
| API-EQUIPO OXICORTE | EQUIPO DE CORTE OXIGENO-GAS | hora | 0.160000 | $6.18 | $0.99 |
| API-ESMERILADORA | ESMERILADORA | hora | 0.160000 | $2.38 | $0.38 |
| Suma de Equipo | $4.83 | ||||
| Costo Directo | $44.70 |